Atascosa County Can't Zone Out a Data Center. Here's What It Rewrote Instead.

"Legally, we do not have statutory authority as a county to implement a moratorium on development," County Attorney Molly Solis told a packed room at the Atascosa County Justice Center in Jourdanton on July 7, according to the Pleasanton Express. "Cities do have that capability. We do not have that."

Anyone pricing acreage in Atascosa County should keep that sentence in mind. Outside city limits, the question of what gets built on the next tract over is mostly settled between two private parties. The county's tools apply later in the process and cover narrower ground. Over the summer of 2026 the county sharpened those tools. A buyer still has to know where each one starts and where it stops.

How the Rumor Played Out

The talk began with a project called Energy Ranch. HC Capital Partners and Herrmann Family Companies announced it in January 2026 as a wholly owned South Texas campus of more than 1,500 acres. A March 16, 2026 HC Capital release describes modular natural-gas generation, with the first 250 MW targeted for early 2028 and an eventual capacity of 1 to 3 GW, at a site about 58 miles south of San Antonio.

By June, residents were asking the county about it. Judge Weldon P. Cude's office put out a statement on June 15. In an August 7 clarification, the county said the property owner had since stated publicly that Energy Ranch is not located in Atascosa County. Curtis Vickers told the July 7 meeting that the project is in Frio County and is not connected to any potential Atascosa project, according to the Pleasanton Express.

A separate site is still unconfirmed. News4SA/WOAI reported on July 1 on a rumored location "a few miles northwest of Jourdanton," spread across two plots totaling more than 1,500 acres. The report named no road or parcel. As of the county's August 7 statement, Commissioners Court had received no request for county action on a data center project.

The rumor itself proved little. What matters more is what the county explained about its own reach while it was answering questions.

The Site Decision Is a Private Transaction

At the July 7 meeting, Judge Cude said roughly nine or ten data center companies had come through his door. "I specifically ask them, 'What are you asking for?' No tax abatements, no PILOT programs, nothing," he said, as reported by the Pleasanton Express. "At that point they tell me the area they are looking at, and there's nothing we can do because that's a private exchange. It's private property rights between two different people."

The county's own Development Transparency & Community Engagement Principles says the same thing in writing. Texas law gives counties "only limited regulatory authority over private development in the unincorporated area." The guide encourages developers to meet with neighbors early, hold voluntary informational meetings and name a community contact. It also states that these steps "may not be required by law."

For a buyer, the practical point is that no zoning map shows what the neighboring ranch can become. The first public sign of a large project may be a fire review or a well permit, and both come after the land deal is done.

What the July 27 Vote Changed

The county did use the authority it has. On July 27, 2026, Commissioners Court voted unanimously to adopt the 2024 International Fire Code and International Building Code with local amendments, effective immediately, the Pleasanton Express reported. Officials said the update responds to concerns about high-hazard facilities such as data centers and battery energy storage systems, known as BESS. The county had been on the 2015 edition. It relies mainly on volunteer fire departments, and the City of Pleasanton's department is the only exception.

The local amendments are where the new rules sit:

Provision What it covers
NFPA 75 adopted by reference Data centers, colocation and cloud facilities, cryptocurrency mining
Third-party fire protection review BESS over 1 MWh, data centers over 100,000 sq ft, high-hazard occupancies
Appendix R, rural standards New subdivisions, residential and commercial developments, large-acreage properties
Appendix R water supply Fire ponds, storage tanks, dry hydrants or other approved sources where municipal water is unavailable
Building code scope Commercial, public, and multifamily of four or more units; not single-family homes, duplexes or triplexes

The amendments set standards for how a facility is designed and reviewed once someone proposes to build it. The equipment question is still open. KSAT reported that when the county fire marshal was asked whether local firefighters had the equipment and training for BESS fires, he answered "No."

Appendix R also reaches ordinary ranch buyers. It calls for address identification visible from the road, and private access roads with adequate width, emergency vehicle access, turnarounds where required, and maintenance good enough for emergency response. Someone planning a lodge, barn complex or ranchette layout on a large tract can ask the Atascosa County Fire Marshal's Office how Appendix R applies to that property before drawing roads.

The One Point Where a Project Has to Go Public

Under the county's guide, a matter comes before Commissioners Court in a posted public meeting only when it needs official county action, "such as consideration of a tax abatement, development agreement, road agreement, or other county approval."

A public vote comes when a project needs something from the county, whether that is an incentive, an agreement or another approval. At the July 7 meeting, county officials said no development agreement had been presented, no abatements or incentives had been requested or approved, and no binding agreements existed. The October 26, 2026 Commissioners Court agenda listed no data center, BESS, abatement, reinvestment zone or road-use item. Its land-related business included a CPS Energy right-of-way permit on Workman Road and an extension of an EOG Resources temporary water line on County Road 413.

That leaves a gap. A developer that needs no abatement, agreement or other county approval has no reason to appear on that agenda. Watching agendas shows a buyer when a project needs the county's signature, and it can miss a project that has quietly bought or leased land.

The positions on the court are on the record. At the July 7 meeting, Commissioners Gillespie and Bowen said they opposed data centers in the county, and Commissioners Eustace and Pawelek said they were neutral until more information was available, per the Pleasanton Express.

Groundwater Is the Lever That Follows Every Tract

The Evergreen Underground Water Conservation District regulates every well, large or small. At the September 10 forum it co-hosted with the county, Dr. Arin Teague explained that groundwater in Texas is a private property right but does not follow fence lines. She described district spacing rules as a "polite fence" between users, according to the Pleasanton Express. At the July meeting she said the state authorizes districts like Evergreen to issue fines of up to $25,000 per day for rule violations.

Evergreen last amended its rules on August 21, 2026. A new well needs registration or a permit before it is drilled. The ordinary domestic and livestock exemption requires a tract larger than 10 acres, allows one exempt well per 10 acres, and caps each well at 25,000 gallons per day. Evergreen's 2026 notice to purchasers says a buyer of property with an active or abandoned well must register the well and/or transfer ownership within 45 days of the property transfer.

The same district rules apply to a ranch buyer's stock well and to any large user's production permit, which makes Evergreen the local regulator that touches both sides of the fence.

A Short Diligence List for Atascosa Acreage Right Now

  1. Ask the seller whether any developer, land agent or utility has approached them about an option, lease or sale, and read the title commitment for recorded options or easements.
  2. Check recent Commissioners Court agendas for abatement, development agreement or road agreement items near the tract.
  3. Ask Evergreen UWCD whether each well on the property is registered, and how its 45-day transfer notice applies to the closing.
  4. If the plan depends on exempt domestic or livestock wells, ask the district how the exemption thresholds apply to the tract.
  5. Before planning a lodge or private road network on large acreage, ask the Fire Marshal's Office how Appendix R access and water-supply standards apply.

FAQ

Is there a confirmed data center in Atascosa County? As of the county's August 7, 2026 statement, Commissioners Court had received no request for action on one, and the October 26 agenda carried none. The northwest-of-Jourdanton site reported in July remains unconfirmed.

Where is Energy Ranch? County officials and the property owner have placed it in Frio County. The developer describes it as a campus of more than 1,500 acres with first power targeted for early 2028.

Does the new building code affect a ranch house? The county building code applies to commercial, public and larger multifamily buildings, and excludes single-family homes, duplexes and triplexes. The fire code's Appendix R rural standards separately name large-acreage properties.

This post is general information, not legal, tax or financial advice. Confirm how any rule applies to your property with the county, Evergreen UWCD or a qualified attorney.

If you're weighing an Atascosa County tract and want the well registrations, recorded rights and nearby county agenda activity checked before you sign, Craig Wilson can work through that due diligence with you. Start a Conversation.